| | None core budget item | Three year funding requirement CHF |
|---|
| 1. Junior Partnership/fundraising officer to support the Partnership coordinator and build the unit. Could be JPO or other. | B | 390,000 |
| 2. 1 Regional Officer to support each of the 4 regional teams in the Secretariat, from 2014. Could be JPO. | C | 1,174,000 |
| 3. Support to Regional Initiative Networks and Centres. Funding for the priority activities. | D | 900,000 |
| 4. STRP programme of work for 2013-2015 (Strategy 1.1, 1.2, 1.4, 1.5, 1.6, 1.7, 1.9, 2.5, 3.1), including the Global Wetland Observing System (GWOS) project (but excluding the RSIS project in item 8 below) | E | 1,905,000 |
| 5. Junior officer as webmaster/social media officer to strengthen the communications team | F | 390,000 |
| 6. IT Officer to, inter alia, drive upgrades in the website and documentation management software, allow for InforMEA participation and support other database management and upgrades. Also to oversee electronic RSIS and Ramsar Sites Database overhaul project | G | 390,000 |
| 7. Interpretation for Standing Committee sub group meetings | I | 75,000 |
| 8. Investment in Electronic RSIS submission and RIS database processes and software | 1 | 400,000 |
| 9. World Wetlands Day (currently funded by Danone) at the current level, i.e., preparation and dissemination of products such as leaflets and posters and other CEPA materials for customization and promotion of WWD (Strategy 4.1) | 2 | 300,000 |
| 10. Emergency Ramsar Advisory Missions for Parties unable to self-fund their missions (Strategy 2.4, 2.6) | 3 | 450,000 |
| 11. Delivery of one CEPA action planning workshop and other CEPA actions to support the Core-funded CEPA activities (Strategy 4.1) | 4 | 300,000 |
| 12. CHF 1 million per annum of resourcing for the Small Grants Fund and CHF 400,000 in other grant funding in order to keep the three current grant programmes operational. (Support to many 2009-2015 Strategies, including 1.3 and 5.1) | 5 | 4,200,000 |
| 13. Annual regional meetings (technical), with enhanced funding in the pre-COP year to fund delegates and meeting costs for COP preparatory regional meetings | 6 | 1,050,000 |
| 14. Sponsorship to bring eligible delegates to COP12 in 2015 (Strategy 3.3, 4.2) | 7 | 1,200,000 |
| 15. 2016-2021 visioning process and 2016-2021 Strategic Plan, with significant input from Contracting Parties and other relevant stakeholders for 2016-2021 | 8 | 250,000 |
| | | |
| | CHF | 13,374,000 |